Task:

At the production site at Erkheim a large number of different consumables ( screws, nails, cramps etc.) are required for the production of wall-, roof- and ceiling-elements. The previously complicated buying process (order, order confirmation, receipt of goods etc.) resulted in high costs which had to be downsized.

Methods:

  • Determination of different models
  • Analysis of current situation
  • Data collection and determination of quantities consumed
  • Product specification for supplier inquiries
  • Negotiation with suppliers
  • Evaluation/assessment of offers received
  • Implementation of the new process


Results and benefit:

The introduction of the Kaban software resulted in a lean and transparent buying process and considerable costs reductions could be achieved.